Building Electrification lab manual Exp No 5 and Sl. No. 5

 

 

 

Department of Electrical Engineering

Subject: Building Electrification Laboratory

By: Palash Das

Lecturer in Electrical Engineering

-------------------------------------------------------

 

Experiment Name: Prepare wiring installation on a board showing control of one lamp, one fan and one socket from one switch board using batten conduit wiring system.

 

Number of Experiment: 04; Sl. No 5

Date of Experiment: 

Date of Submission:

 

Aim: ✓✓To familiar about  batten wiring system with load  connection in domestic applications.

         ✓✓Prepare wiring installation on a board showing control of one lamp, one fan and one socket from one switch board using batten conduit wiring system.

 

Theory:

This system of wiring is suitable for low pressure (upto 250 volts) installation. This is specially suited for places where acid or alkali fumes are likely to be present. This is extensively used for lighting installation, residential, commercial or industrial excepting workshops.

Here the circuit consists of one lamp, one fan and one socket from one switch board.

In this type of wiring PVC cables, single core or twin-core, are used on teak wood battens of at least 10mm thick. The width of the batten depends on the number and size of cables used. The available sizes are 13 mm. (for one 1.5 sq mm. twin core or two single core cables), 19 mm, 25 mm. etc. The T.W. battens are fixed on walls with wood or PVC plugs and wood screws at intervals not exceeding 75 cm. PVC cables are run on the battens and fixed to the battens with the help of link and clips already fixed on the battens with brass pins or iron nails.

 

Extra note:

According to IS.S., the following points are to be observed when installing batten wiring:

(1)    TW. battens shall be at least of 10 mm thick and of suitable width to accomodate all the cables.

(2)    (ii) These battens are to be fixed on walls or ceilings by flat head wood screws to wood or other plugs at an interval not exceeding 75 cm.

(3)     Link clips shall be so arranged that one single clip is not to hold more than two twin-core or four single core cables. These clips are fixed on wood battens with brass pins or iron nails and are to be spaced at an interval of 10 cm in the case of horizontal run and 15 cm in case of vertical run

(4)     In case of any chance of the wiring being damaged, such wiring is to be  covered with sheet metal protective covering or to be drawn through heavy gauge metal conduit. Wooden bushes are to be provided at the end of conduits

(5)    While passing through floors or walls, porcelain tubes are to be used.

(6)     The wires must not be bent to a radius less than six times the overall the cable.

(7)    The ends of the cable must be sealed in compounds in damp situations.

(8)    The wiring shall, after erection, be painted with one coat of oil-less point

 

Circuit and Image :

Draw the circuit and batten wiring image.

 

Specification:

Sl. No

Component used

No of component

Rating

 

Fuse

 

1

 

1

 

Indicator

 

Switch

3

 

 

Lamp

1

 

 

Fan

1

 

 

Socket

1

 

 

S D B

1

 

 

Connector wiring

 

 

 

Required instrument:

1.       Line tester

2.       Screw driver- write it’s dimension

3.       Poker.

4.       Cutter cum stripper

5.       Self adjustable stripper  cutter.

Precaution:

√√Connect  the circuit as directed by the guide

√√ Use predefined wire size  for the assigned load.

√√Earthing connection should be used for load starting from energy meter.

√√For light, fan and heating loads the fuse  rating is not to be less than the total load currents of the circuit.

√√Minimum size of battenof at least 10 mm thick

                  Can not be used in places exposed to sun and rain.

 

Conclusion:

 

 


No comments:

Post a Comment

Name of the experiment: conduct the No load and Blocked root test on a given three phase squirrel cage induction motor and determine the equivalent circuit parameters.

Name of the experiment: conduct the No load and Blocked root test on a given three phase squirrel cage induction motor and determine the equ...